UPS, AMF, ATS and Generator Load Testing - January 2021

06 January 2021, in Data Centre

As part of Web Wiz planned and preventative maintenance regime we will be carrying out load testing on the Uninterruptible Power Supplies (UPS), Automatic Mains Failure (AMF), Automatic Transfer Switching (ATS) and Neutral Gas Powered Generator Systems at our Data Centre.

During the test period, the UPS systems will take the full load of the Data Hall while the Generator comes online and the AMF moves the facility to Generator Power.  

The Generator will take the full load of the facility for a 20 minute period, once the test is completed power to our facility will return to our usual mix of Solar, Battery, and Utility Power.

Automatic Transfer Switching (ATS) will move rack power from "A" to "B" Power Feeds before returning each Rack to "A" Power Feeds.

At-risk period:
Start Date: 12th January 2021

Times work will be carried out:
Start Time: 08:00
End Time: 08:30

Service Impact:
No impact to services is expected.

Reason:
This routine maintenance is essential to ensure that the UPS, Generator and Automatic Switching systems work as intended and are able to provide power to our Data Centre in the unlikely event of a Power Outage.



Emergency Fibre Maintenance - 10th December 2020

09 December 2020, in Network, Data Centre

We have received a last-minute notification from one of our fibre suppliers of emergency maintenance that will affect our Virgin Media circuit to our Bournemouth Data Centre overnight.  

Traffic that would be carried over the circuit will be rerouted and there will be no impact to service, however service should be considered at risk due to the loss of resilience.

Start of work - At-Risk period:
Start Date: 10th December 2020 Start Time: 00:00

End of work - At-Risk period:
Risk End Date: 10th December 2020 Start Time: 06:00

Service Impact:
No impact on the live services is expected, however service should be considered at risk due to the loss of resilience. 

Reason:
As often the case with Virgin Media the only information provided is they need to carry out Emergency Planned Engineering Works (PEW) on the circuit.



Emergency Fibre Maintenance - 14th November 2020

13 November 2020, in Network, Data Centre

We have received today notification from one of our fibre suppliers of emergency maintenance that will affect our CenturyLink / Level 3 transit to our Bournemouth Data Centre. 

Traffic that would be carried over the circuit will be rerouted and there will be no impact to service, however service should be considered at risk due to the loss of resilience.

Start of work - At Risk period:
Start Date: 14th November 2020 Start Time: 07:30

End of work - At Risk period:
Risk End Date: 4th November 2020 Risk End Time: 19:00

Service Impact:
No impact on the live services is expected, however service should be considered at risk due to the loss of resilience. 

Reason:
Emergency works taking place on our provider's fibre platform. They are required to alter our fibre due to power development works happening within the area, they will be moving the fibres so that they are out of scope from this work.



Data Centre Fibre Outage

22 September 2020, in Network, Data Centre

Our Virgin Media fibre circuits to our Bournemouth Data Centre have loss connectivity. This has been raised with our upstream provider who are investigating the issue.

Traffic that would have been carried over the circuits has automatically rerouted and there is no impact to service at this time, however service should be considered at risk due to the loss of resilience.

Update 19:10
Connectivity has been restored and the service has been returned to full resilience. No reason for the outage has been given as yet.

We will continue to monitor the fibre circuit and will update this page if the situation changes. 



UPS, AMF, ATS and Generator Load Testing - August 2020

21 August 2020, in Data Centre

As part of Web Wiz planned and preventative maintenance regime we will be carrying out load testing on the Uninterruptible Power Supplies (UPS), Automatic Mains Failure (AMF), Automatic Transfer Switching (ATS) and Neutral Gas Powered Generator Systems at our Data Centre.

During the test period, the UPS systems will take the full load of the Data Hall while the Generator comes online and the AMF moves the facility to Generator Power.  

The Generator will take the full load of the facility for a 20 minute period, once the test is completed power to our facility will return to our usual mix of Solar, Battery, and Utility Power.

Automatic Transfer Switching (ATS) will move rack power from "A" to "B" Power Feeds before returning each Rack to "A" Power Feeds.

At Risk period:
Start Date: 25th August 2020

Times work will be carried out:
Start Time: 08:15
End Time: 08:45

Service Impact:
No impact to services is expected.

Reason:
This routine maintenance is essential to ensure that the UPS, Generator and Automatic Switching systems work as intended and are able to provide power to our Data Centre in the unlikely event of a Power Outage.



Page  123...4>



Become a Fan on Facebook Follow us on Twitter Connect with us on LinkedIn Community Forums Web Wiz Blogs Web Wiz News
About Web Wiz | Contact Web Wiz | Terms & Conditions | Cookies | Privacy Policy

Web Wiz is the trading name of Web Wiz Ltd. Company registration No. 05977755. Registered in England and Wales.
Registered office: Web Wiz Ltd, Unit 18, The Glenmore Centre, Fancy Road, Poole, Dorset, BH12 4FB, UK.

Prices exclude VAT unless otherwise stated. VAT No. GB988999105 - $, € prices shown as a guideline only.

Copyright ©2001-2021 Web Wiz Ltd. All rights reserved.